Build – 1st Week; 27 Jan to 03 Feb 2013

Sunday 03: Working on Sunday!. Weather not brilliant, but rain not heavy enough to stop work.

Saturday 02: More of the same; concrete gets poured.

Friday 01 Feb: More of the same; work starts on shuttering for the support wall.

Thursday 31: Work starts on the concrete base for the retaining wall and the eastern boundary wall is complete.

Wednesday 30: More digging.

Tuesday 29 and Monday 28: I took videos of the actoin – bagger digging – but have still to work out how to get stills from teh video!.

Sunday 27 Jan: The plot is marked out. Work starts tomorrow, after 5 3/4 years of waiting!

 

[nggallery id=1]