Sunday 03: Working on Sunday!. Weather not brilliant, but rain not heavy enough to stop work.
Saturday 02: More of the same; concrete gets poured.
Friday 01 Feb: More of the same; work starts on shuttering for the support wall.
Thursday 31: Work starts on the concrete base for the retaining wall and the eastern boundary wall is complete.
Wednesday 30: More digging.
Tuesday 29 and Monday 28: I took videos of the actoin – bagger digging – but have still to work out how to get stills from teh video!.
Sunday 27 Jan: The plot is marked out. Work starts tomorrow, after 5 3/4 years of waiting!