Build – 3rd Week; 11 Feb to 17 Feb 2013

Friday 15: Concrete is poured into the lower level roof – the garage roof is already finished. The props used are professional, unlike many building sites where wooden poles are cut, supposedly to the same length.

Thursday 14: The hole for the rain water tank is finished off – the ‘bagger’ can’t handle neat corners of a smooth base. In a short time, the base is formed!

Tuesday 12 & Wednesday 13: Heavy rain on both days made any serious work impossible. The guys have worked non-stop for the past two weeks, so a rest is necessary anyway, in our opinion.

Monday 11: The earth from the last part of the retaining wall, from the technical room to the south-west end of the site, along the road is cleared.

[nggallery id=6]