Sunday 10: The earth from the last part of the retaining wall, from the technical room to the south-west end of the site, along the road is cleared.
Saturday 09: Forming the floor of the lower level.
Friday 08: Plumbers (‘plumbists’ per Vasko) install the pipes for the sewage to the septic tank.
Thursday 07: Digging the foundation for the base of the internal walls of the lower level.
Wednesday 06: Shuttering comes down from the garage wall.